Time line based on 2200 square foot house:
- 4 weeks for design drawings
- 8 weeks log milling and delivery
- 1 week erect structure
- 1 week install window and door components & install roof panels
- 2 weeks interior framing
- 2 weeks finish interior non-log walls
- 3 weeks trim, cabinets, fixtures, flooring
- 2 weeks misc
- total 24 weeks start to finish